Opening Day Update (Friday, June 27)

Members, Our pool has passed initial electrical and plumbing inspections. We failed the mechanical inspection earlier this week and now wait several days for a single part. We requested a temporary certificate of occupancy for 30 days to allow us to open the pool...

Opening Day Update (Friday, June 20)

Members, We are disappointed to inform you that Opening Day will not be Monday, June 23rd. Several factors to comply with standards for final inspections are unfortunately currently still in play.  We will send additional notices as soon as we receive information. We...

Opening Day Update (Tuesday, June 10)

Your Swimming Hole Board hopes you are having a good start to the summer. We look forward to seeing you at the pool very soon.  As we hope you know, we are on site every day working with our contractors, committed to seeing our project through. They still tell us to...